Status of El Paso City Parks and Recreation Projects

Hawkins Aquatic Center Upgrade
An installation of a new HAVC system for the restrooms and office area of Hawkins Aquatic Center, 1500 Hawkins Blvd. will be conducted by Johnson Controls from Monday, January 18th – Thursday, January 28th, 2010. During this time, heating or cooling will not be available for those areas; however the pool will remain open.

Franklin Park Construction (6050 Quail Ave.)
Construction continues at the park with an expected completion of April 15, 2010. A new lighted walking path, picnic area and benches, new perimeter lighting, and ADA access to the playground are some of the new amenities.

Cohen Baseball Stadium Canopy Replacement(700 Gateway North)
Canopy replacement is expected to start March 1 with an estimated eight week completion period.

Pavo Real Aquatic Center Bath House (110 Presa Place)
Construction is scheduled to begin approximately February 1, 2010 which will include new showers and stalls and other upgrades to meet ADA requirements. Expected completion date is May 15, 2010.

Westside Sports Complex (201 Isela Rubalcava St.)
Phase 2 of the Complex will add five more soccer fields; four lighted. Opening is estimated for fall of 2010.

Pat O’Rourke Recreation Center Update (701 N. Montana St.)
Construction continues with an expected opening late summer/early fall 2010.