Construction on the Joe Battle (Loop 375) / Zaragoza (FM 659) Direct Connectors Project began today.
The proposed project will construct two direct elevated connectors.
**One connector will be constructed for traffic traveling in the northbound direction of Joe Battle (Loop 375) onto northeast Zaragoza Rd. (FM 659).
**One connector will be constructed for traffic traveling in the southwest direction of Zaragoza Rd. (FM 659) onto southbound Joe Battle (Loop 375).
CLOSURES:
The southbound Joe Battle Blvd. left lane between Montwood Dr. and the Montwood Entrance Ramp will be closed starting tomorrow, January 4 at 9 a.m. and continued closed through April 2012.
The construction crews will be building a retaining wall.
There will be a right lane closure southbound on Joe Battle (Loop 375) from the Montwood Exit Ramp to the Montwood Entrance Ramp on Thursday, January 5 and Friday, January 6 from 9 a.m. to 4 p.m.
Crews will be placing concrete barriers on the shoulder.