Tuesday, April 14, 2009

Street Resurfacing

Street Resurfacing projects for week of April 13

The City of El Paso Street Department will be working on the following resurfacing projects:

STREET NAME
FROM
TO
STATUS
PIEDMONT DR
SAN MATEO LN
ROBINSON AVE
PAVING
CHESTERFIELD AV
HOWZE ST
DEAD END
PAVING
WAINRTIGHT DR
TROWBRIDGE AVE
TIMBERWOLF DR
PAVING
MESCALERO DR.
MONTANA AVE
DEAD END
PAVING
MORROW CT
STOCKWELL LN
GALLOWAY DR
PAVING
HARDAWAY ST
TROWBRIDGE AVE
MONTANA AVE
MILLING
WILLIE SANCHEZ LN
PAISANO DR
GATEWAY WEST
MILLING
SAN MARCIAL ST
ALAMEDA AVE
PAISANO DR
SURFACING RECYCLING


Project scope includes; milling of the existing street, replacement of damaged curbs and gutters, and applying a new asphalt riding surface.
Concrete work is the removal, replacement or installation of curb & gutter, sidewalks, ADA ramps, and alley aprons. It may also include the installation of aprons around water valves, monuments and manholes.
Sub-grade/base work is the removal and replacement of unstable base course and sub-grade prior to resurfacing or resumption of resurfacing operations.
Milling is the removal of the existing surface course to prepare for heating (edge mill) or paving (full mill).
Paving is the laying of new asphalt on a prepared surface.
Proper traffic control measures will be in place to direct the traveling public through these areas for this period.
The resurfacing schedule is a plan that may be modified due to weather or other unforeseen events.